Question1: Which part of TOGAF describes taxonomies for categorizing the outputs of architecture activity in terms of reuse?

Question2: Which one of the following categories from the Document Categorization model consists of the normative parts of TOGAF which are considered central to its usage?

Question3: Which of the following best completes the sentence? The Architecture Repository __________________.

Question4: Which of the following is an objective of the Preliminary Phase?

Question5: Complete the sentence. All of the following describe a purpose of an Architecture Compliance review, except ______________.

Question6: A key step in validating a proposed target architecture is to consider what may have been forgotten. What technique does TOGAF recommend to address this issue?

Question7: Which of the following describes an objective of the Preliminary Phase?

Question8: Scenario:
Please read this scenario prior to answering the question
The ABC company is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The company Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their planning and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many of the participants have voiced concerns about the sweeping scope of the initiative. Others are confident that they know a solution that will work. During the meeting, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

Question9: Which of the following does TOGAF describe as a package of functionality defined to meet business needs across an organization?

Question10: Which of the following best describes the TOGAF Architecture Development Method?

Question11: In which ADM phase is the goal to ensure that the architecture achieves its original target business value?

Question12: What part of the Architecture Repository holds specifications to which architectures must conform?

Question13: Scenario:
Please read this scenario prior to answering the question
ABC LLC is a vacation property management firm that is growing through acquisition. It manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed in each property is that they use a standard financial reporting system to report their financials ID the headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the LLC property business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields.
The LLC has a mature enterprise architecture (EA) practice and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial engagement, the company has embraced an Architecture Vision to adopt an enterprise application that is tailored to the needs of the hospitality industry.
Refer to the scenario
Your role is that of Chief Architect. You have been asked to recommend the best approach to take in this architecture engagement to realize the CEO's vision.
Based on TOGAF 9, which of the following is the best answer?

Question14: TOGAF uses a version numbering convention to illustrate the evolution of the Baseline and Target Architecture Definitions. Which version number in this convention indicates a high-level outline of the architecture?

Question15: Scenario
Please read this scenario prior to answering the Question
You are working as a consultant to the Chief Architect at a government agency responsible for securing all government communications and information systems. The agency has recently received funding for a program that will upgrade the reliability and performance of its secure communication systems which provide real-time, highly secure communication of voice, video, and message data to remote locations around the world.
The agency has an established enterprise architecture (EA) capability based on TOGAF 9. The Executive Director of the agency is the sponsor of the EA capability.
Since reliable, high-performance, and secure communications are essential to preserving national security, the Executive Director has placed more stringent requirements for the architecture for the upgraded system. It must be able to provide assurance and verification of specific performance measures on the key services that are most crucial for system operation. Focusing on these service-level details and specific measurements will allow more stringent requirements to be enforced in service contracts. It will also provide a high degree of assurance that necessary performance is being delivered and that notifications will occur if any critical service fails to perform as required.
A portion of the program budget has been allocated to context a review of the EA. The scope of the review is to evaluate the processes, content and governance of the EA capability to ensure that the higher target performance and service levels required by the upgraded system can be achieved.
The Chief Architecture has noted that the core EA artifacts that have been used since TOGAF 9 was introduced are not adequate to describe these new capabilities. The artifacts do not have explicit provisions for defining the in-depth measurement requirements regarding specific services required for the system. She has learned that certain services within the current system have service measurement implementations that match some of the new requirements, but they are only used in a few areas.
Recent EA efforts at another national agency have produced generalized high-performance communication system models to realize similar requirements in a critical defense system involving secure communications. It is possible that these models may be useful for the upgrade program.
Refer to the Scenario
You have been asked to make recommendations for tailoring the Architecture Content Metamodel to accommodate the requirements of the upgraded system.
Based on TOGAF, which of the following is the best answer?

Question16: Which of the following best describes the TOGAF Architecture Governance Framework?

Question17: According to TOGAF, which of the following steps in Phases B, C, and D occurs before development of the baseline or target architectures?

Question18: Which ADM phase establishes the connection between the architecture organization and the implementation organization through the Architecture Contract?

Question19: Which one of the following is defined by TOGAF as: the fundamental organization of a system embodied in its components, their relationship to each other, and the principles guiding its design and evolution?

Question20: When using a cycle of the ADM to establish an Architecture Capability as described in TOGAF Part VII, which architecture would describe the infrastructure requirements?

Question21: Complete the sentence. The Architecture Landscape is divided into three levels, Strategic, Segment and
____________.

Question22: Scenario
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for an enterprise architecture project team within a leading multinational pharmaceutical and medical devices manufacturer. Its brands include numerous household names for medications and first aid supplies.
The company has a long history of innovating new treatments for many common illnesses and diseases.
Prior to launching a new treatment, the company has to demonstrate Its effectiveness and safety in a set of clinical trials that satisfy the regulatory requirements of the countries in the target markets. All clinical trials are undertaken by its research laboratories, which employ over 10,000 people at separate facilities in the United Kingdom, United States, Sweden, France, Canada, India, China and Japan. In addition to internal research and development activities the company is also involved in publicly funded collaborative research projects, with other industrial and academic partners.
The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners.
The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners.
The Enterprise Architecture group is a mature organization. They use the TOGAF 9 ADM with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.
She has stated that the changes to the enterprise architecture for the new system will need to be rolled out in stages on a regional basis that minimizes disruptions to ongoing clinical trials.
Refer to the Scenario
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based on TOGAF, which of the following is the best answer?

Question23: According to TOGAF, how is the Enterprise Continuum used in organizing and developing an architecture?

Question24: Scenario:
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.
The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels. In order to do so this will require wind turbines to be installed over large areas of higher wild resources. In particular offshore wind farms can contribute substantially more energy than land stationed trubines.
The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system that will produce up to 20% more energy. This will allow the production of significantly more saleable energy. This new design is ready to go into production.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.
Refer to the Scenario
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

Question25: Complete the sentence. The Enterprise Continuum provides methods for classifying architecture artifacts as they evolve from.

Question26: According to TOGAF, which of the following best describes the purpose of the Architecture Definition Document?

Question27: Complete the sentence. The practice by which the enterprise architecture is managed and controlled at an enterprise level is known as____________.

Question28: Which of the following best describes the TOGAF classification in Phase H for a re-architecting change?

Question29: In which section of the TOGAF template for Architecture Principles would a reader find the answer to the question of "How does this affect me"?

Question30: Complete the sentence. All of the following are parts of the conceptual structure of the TOGAF Architecture Governance Framework, except ______

Question31: Which of the following best describes a purpose of the Business Scenarios technique?

Question32: Which ADM phase provides architectural oversight of the implementation?

Question33: Which of the following describes the TOGAF classification in Phase H for a simplification change?

Question34: What document is used to initiate a TOGAF ADM cycle?

Question35: According to TOGAF, which of the following best describes the purpose of an Architecture Definition Document?

Question36: Which section of the TOGAF document contains a structured metamodel for architectural artifacts?

Question37: Complete the sentence. TOGAF defines five criteria for a good set of principles: Complete, Consistent, Stable, Understandable and_______.

Question38: Which part of TOGAF describes a step-by-step approach to developing an enterprise architecture?

Question39: Which of the following describes an objective of Phase G: Implementation Governance?

Question40: Scenario:
Please read this scenario prior to answering the question
The ABC company started as an accounting and financial services company. It has expanded over the years and is now a leading North American IT and Business Services provider.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings. Senior partners must become team players, working to support the broader needs of the company and its shareholders.
The Enterprise Architecture team has been working to create the company's Enterprise Architecture framework to address these issues. The team has defined a preliminary framework and held workshops with key stakeholders to define a set of principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period.
An Architecture Review Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the Enterprise Architecture program. The Enterprise Architecture framework is based on TOGAF 9.
As the EA team prepare to formulate an Implementation plan, they have been asked by the CIO to assess the risks associated with the proposed architecture. He has received concerns from senior management that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been assigned to the role of Chief Enterprise Architect.
You have been asked to recommend an approach to satisfy the concerns raised.
Based on TOGAF 9, which of the following is the best answer?

Question41: Complete the sentence. The Architecture Landscape is divided into three levels, Capability, Segment, and
____________.

Question42: An association of companies has defined a data model for sharing inventory and pricing information.
Which of the following best describes where this model would fit in the Architecture Continuum?

Question43: Which of the following describes an objective of Phase F: Migration Planning Phase?

Question44: Scenario:
Please read this scenario prior to answering the question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well- developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.] One of the earliest initiatives in the Enterprise Architecture program was the definition of a set of architecture principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
Based on TOGAF 9, which of the following is the best answer?

Question45: In which ADM phase does the value and change management process determine the circumstances under which the Enterprise Architecture is permitted to change after deployment?

Question46: Scenario
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within the staff headquarters of a large hotel chain. The chain manages over 500 hotels across North America and Canada, with another 230 hotels internationally in the United Kingdom, Europe, Australia and New Zealand. Unlike other hotel chains, which are often a mix of company-owned and franchised units, each hotel in the chain is an independently owned and operated franchise. Many of the hotels use the same internal IT systems that they used before they joined the franchise. Until recently, the only requirement that has been placed on each hotel is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis.
The CEO of the chain has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new support services including worldwide reservations, global, national and regional marketing as well as consolidated financial, logistics, and yield management. This strategy is part of the long-term commitment to enhance the brand image and drive superior revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.
These changes will provide the chain with improved utilization of its capacity and more efficient operations.
The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key national and regional markets to improve yields.
The chain has a mature enterprise architecture practice based in its headquarters and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chain, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the chain has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision.
Based on TOGAF, which of the following is the best answer?

Question47: In which part of the ADM cycle do building block gaps become associated with work packages that will address the gaps?

Question48: Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to
"leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

Question49: Complete the sentence. The Business Transformation Readiness Assessment technique is primarily focused on ___

Question50: Which one of the following best describes a primary use of the Architecture Vision document?

Question51: Complete the sentence. During the implementation of an architecture, if the original Architecture Definition and requirements are not suitable, a ____ may be submitted to initiate further architecture work.

Question52: In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

Question53: Complete the sentence. The Integrated Information Infrastructure Reference Model (III-RM) is an example of a (n) ______ Architecture reference model

Question54: Scenario:
Please read this scenario prior to answering the question
The ABC company is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business.
The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture. The company has selected TOGAF 9 as the basis for its Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
You are serving as the Chief Architect.
You have been asked to recommend the approach to take in the Preliminary Phase to ensure that the Corporate Board's concern is addressed.
Based on TOGAF 9, which of the following is the best answer?

Question55: Which one of the following is an objective of the Preliminary Phase of the ADM?

Question56: Which Architecture domain is recommended to be the first architecture work undertaken in the ADM cycle?

Question57: Which of the following best describes the purpose of the Business Transformation Readiness Assessment technique?

Question58: An ADM cycle can be used to establish an Architecture Capability within an organization. Which architecture produced in such a cycle would describe the architecture processes and organization structure?

Question59: Which ADM phase starts with the receipt of a Request for Architecture Work from the sponsoring organization?

Question60: According to TOGAF, which of the following terms is defined as the key interests that are crucially important to stakeholders?

Question61: Which of the following does TOGAF describe as "a formal description of a system, or a detailed plan of the system at component level to guide its implementation"?

Question62: According to TOGAF, which of the following best describes the purpose of the Architecture Roadmap?

Question63: Complete the sentence. According to TOGAF, the simplest way of thinking about the Enterprise Continuum is as a _____

Question64: Which one of the following is an objective of Phase A, Architecture Vision?

Question65: Complete the sentence. As the architecture evolves, the assets in the Solutions Continuum progress towards a (n) _____

Question66: Complete the sentence. According to TOGAF, an objective of Phase G, Implementation Governance, is to______________.

Question67: Complete the sentence. A server consolidation project that does not change the operating characteristics of the applications would require _____.

Question68: Which one of the following lists the main components within the TOGAF Architecture Repository?

Question69: Scenario:
Please read this scenario prior to answering the Question.
The ABC Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials. The Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years.
The company Architecture Development Method is strictly based on TOGAF 9 with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. The project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.
He has stated that the changes to the enterprise architecture for the new system will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
Refer to the Scenario
You are serving as the Lead Architect for the project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based on TOGAF 9, which of the following is the best answer?

Question70: According to TOGAF, which of the following are the architecture domains that are commonly accepted subsets of an overall enterprise architecture?

Question71: Complete the sentence. TOGAF covers the development of four architecture domains, Business, Data, Technology and ___________.

Question72: Which ADM Phase includes obtaining approval for the Statement of Architecture Work?

Question73: Which of the following is a true statement about the TOGAF Technical Reference Model?

Question74: Complete the sentence. TOGAF describes the role of an Architecture Contract as_______.

Question75: Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well- developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
During the initial meeting of the Common ERP Deployment architecture project team, a number of alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

Question76: Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
Refer to the Scenario
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?

Question77: Which of the following best describes the class of information known as the Reference Library within the Architecture Repository?

Question78: In which of the following ADM Phases do building blocks become implementation-specific?

Question79: Which pair of the following responses best completes the sentence? Architecture building blocks
____, whereas Solution Building blocks ____

Question80: Complete the sentence. The Requirements Management process is used to______.

Question81: Which of the following does TOGAF recommend for use in developing the Architecture Vision?

Question82: Which of the following describes the TOGAF Technical Reference Model?

Question83: Which of the following is described by the TOGAF Architecture Content Framework as a type of artifact that shows relationships between things?

Question84: Which of the following best describes the purpose of the Architecture Vision?

Question85: Which of the following best describes the Integrated Information Infrastructure Reference Model?

Question86: Which of the following best describes the need for the ADM process to be governed?

Question87: Scenario:
Please read this scenario prior to answering the Question
You have been assigned the role of Chief Enterprise Architect within a leading North American information technology services company. The company has a number of service portfolios including infrastructure, applications, business process outsourcing, accounting, and financial services.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management within the company has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of an Enterprise Architecture prog-am based on TOGAF 9. An Architecture Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Enterprise Architecture team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period. This includes a solution architecture including three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the senior partners that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF 9, which of the following is the best answer?

Question88: According to TOGAF, which of the following define general rules and guidelines for the use of assets across the enterprise?

Question89: Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company has defined a strategic architecture to improve its ability to meet consumer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in several of the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A Based on all of these factors they have produced a risk assessment.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
Refer to the Scenario
The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete. You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?

Question90: Complete the sentence. The key purpose of Gap Analysis is to _____

Question91: Which one of the following statements about viewpoints is correct?

Question92: Which one of the following best describes an Architecture Compliance Review?

Question93: Which of the following best describes the purpose of the Architecture Requirements Specification?

Question94: TOGAF uses a version numbering convention to illustrate the evolution of the Baseline and Target Architecture Definitions. Which version number in this convention indicates a formally reviewed, detailed architecture?

Question95: Which one of the following describes classification methods for architecture and solution arti-facts within the Architecture Repository?

Question96: Which of the following does the TOGAF ADM recommend for use in developing the Architecture Vision?

Question97: The Requirements Management Phase is responsible for which one of the following activities?

Question98: Which one of the following does TOGAF state is an objective for Phase A: Architecture Vision?

Question99: Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.
The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information Systems Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing applications?
2. What non-procurement applications will need to be integrated with any new procurement applications?
3. What data will need to be shared?
Refer to the Scenario
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.] You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.
Based on TOGAF 9, which of the following is the best answer?

Question100: Which one of the following is a key objective of Phase A of the TOGAF ADM?

Question101: Which phase of the ADM establishes a set of Principles?

Question102: Which of the following does TOGAF provide as a set of reference materials for establishing an architecture function within an organization?

Question103: Which one of the following provides a foundation for making architecture and planning decisions, framing policies, procedures, and standards, and supporting resolution of contradictory situations?

Question104: In which phase of the ADM cycle do building blocks become implementation-specific?

Question105: Complete the sentence. According to TOGAF, a ______________is a representation of a system from the perspective of a related set of_____________.

Question106: Scenario:
Please read this scenario prior to answering the question
The ABC company is the prime contractor for the Telesto Unmanned Spacecraft program. Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The company is moving aggressively to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
To achieve this goal, the company needs to define Baseline and Target Architectures. These architectures must address key stakeholders' concerns such as:
1. What groups of people should be involved in procurement-related business processes?
2. What current applications do those groups use?
3. Which procurement-related business processes are supported by zero, one, or many existing applications?
4. What are the overall lifetimes of the Request for Proposal and Purchase Order business objects? What non-procurement applications will need to be integrated with any new procurement applications?
5. What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch. The company prefers to implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle. The company is using TOGAF for its internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture Development Method (ADM) projects.
The architecture development project has just completed its Architecture Context iteration cycle and is about to begin the Architecture Definition iteration cycle.
Refer to the Scenario.
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?
A: In the early iterations of the Architecture Definition:
Describe the Baseline Business Architecture with a Baseline Business Process catalog

Describe the Baseline Application Architecture with a Technology Portfolio catalog

Describe the Baseline Data Architecture with a Data diagram

In the later iterations of the Architecture Definition:
Describe the Target Business Architecture with an Actor/Process/Data catalog

Describe the Target Application Architecture with a System/Technology matrix

Describe the Target Data Architecture with a Data Dissemination diagram

B: In the early iterations of the Architecture Definition:
Describe the Target Business Architecture with a Business Service/Function catalog and a

Business Interaction matrix
Describe the key business objects with Product Lifecycle diagrams

Describe the Target Application Architecture with Application Communication diagrams and an

Application Interaction matrix
Describe the Target Data Architecture with a Data Entity/business Function matrix and a System/

Data matrix
In the later iterations of the Architecture Definition:
Describe the Baseline Business Architecture with a Business Service/Function catalog and a

Business Interaction matrix
Describe the Baseline Application Architecture with a System/Organization matrix and a System/

function matrix
Describe the Baseline Data Architecture with a Data Entity/Data Component catalog

C: In the early iterations of the Architecture Definition:
Describe the Target Business Architecture with a Business Service/Function catalog and an

Organization/Actor catalog
Describe the key business objects with Data Lifecycle diagrams

Describe the Target Application Architecture with Application Communication diagrams and an

Application Interaction matrix
Describe the Target Data Architecture with a System/Data matrix

In the later iterations of the Architecture Definition:
Describe the Baseline Business Architecture with a Business Service/Function catalog and a

Business Interaction matrix
Describe the Baseline Application Architecture with an Application and User Location diagram and a

System/Function matrix
Describe the Baseline Data Architecture with a Data Entity/Data Component catalog

D: In the early iterations of the Architecture Definition:
Describe the Baseline Business Architecture with an Organization/Actor catalog

Describe the Baseline Application Architecture with a System/Function matrix

Describe the Baseline Data Architecture using a Data Entity/Data Component catalog

In the later iterations of the Architecture Definition:
Describe the Target Business Architecture with an Organization/Actor catalog

Describe the Target Application Architecture using Application Communication diagrams and an

Application Interaction matrix
Describe the Target Data Architecture with a System/Data matrix

Question107: According to TOGAF, which of the following is a characteristic of a Foundation Architecture?

Question108: According to TOGAF, in which sequence should Application Architecture and Data Architecture be developed in Phase C?

Question109: Which model within TOGAF is intended to assist with the release management of the TOGAF specification?

Question110: Complete the sentence. TOGAF covers the development of four architecture domains, Application, Business, Data and__________.

Question111: In Phases B, C, and D which is the final step in each phase?

Question112: Complete the sentence. In the Preliminary Phase, all of the following are part of preparing the organization to undertake successful enterprise architecture, except __________.

Question113: In the Preliminary Phase, which of the following drives the requirements and performance metrics when scoping the enterprise architecture work?

Question114: Scenario:
Please read this scenario prior to answering the question
The ABC company specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics.
However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
The company has used T0GAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9 framework. All of the company's enterprise architects have been trained and certified on TOGAF 9. Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Scenario
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

Question115: Scenario:
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within a vacation property management firm that has been growing through acquisition. The firm manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed on each property is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields.
The firm has a mature enterprise architecture practice and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the firm has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to justify the best approach for architecture development to realize the CEO's vision.
Based on TOGAF 9, which of the following is the best answer?

Question116: Which section of the TOGAF template for Architecture Principles highlights the requirements for carrying out the principle?

Question117: According to TOGAF, who usually initiates a Request for Architecture Work?

Question118: In Phases B, C, and D which is the first step in each phase?

Question119: Complete the sentence. The Solutions Continuum represents implementations of the architectures at corresponding levels of the _______________.

Question120: Scenario
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to leverage the synergies that should have been possible as a result of the merger. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise- wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
Refer to the Scenario
As part of the process for establishing the Enterprise Architecture department, you are developing a set of architecture principles to guide the activities.
You need to recommend the best approach for this work.
Based on TOGAF, which of the following is the best answer?

Question121: Which of the following best describes an approach for adapting the ADM in the situation where business principles dictate that a packaged solution be used?

Question122: Scenario:
Please read this scenario prior to answering the question
The ABC company is an international agricultural company exporting bulbs, flowers and seeds worldwide.
It is headquartered in Rotterdam in the Netherlands, and has sales and distribution centers in over 60 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self-directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
The company international operations are subject to various legal and regulatory requirements. In areas such as genetically modified seeds, governmental controls are strictly enforced and compliance is critical.
Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested information about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the guiding framework for the development and evolution of the Enterprise Architecture practice.
Refer to the Scenario
You have been appointed as the Lead Consultant.
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of all these parties.
Based on TOGAF 9, which of the following is the best answer?

Question123: Which section of the TOGAF template for defining principles should highlight the requirements for carrying out the principle?

Question124: Which of the following statements about TOGAF Building Blocks is true?

Question125: Which one of the following statements about the Requirements Management phase is true?

Question126: Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to
"leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application to consolidate information from several applications that exist across the lines of business. The application will be used by all business units and accessed by suppliers through well defined interfaces.
Refer to the Scenario
As part of the process for establishing the Enterprise Architecture department, you are developing a set of architecture principles to guide the activities.
You need to specify the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

Question127: Scenario:
Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Lead Enterprise Architect of an international agricultural company that exports bulbs, flowers and seeds worldwide. The company has its headquarters in the Netherlands, and has sales and distribution centers in over 30 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self-directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management team is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
The international operations of the company are subject to legal and regulatory requirements for each country where they operate. The production of genetically modified seeds has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned about the risks posed in this complex global environment, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Governing Board, legal staff, auditors and the research organization.
Based on TOGAF 9, which of the following is the best answer?

Question128: Complete the sentence. All of the following are sections of the recommended template for defining Architecture Principles, except ___________

Question129: What level of the Architecture Landscape provides a long-term summary view of the entire enterprise?

Question130: Which ADM phase is responsible for assessing the performance of the architecture and making recommendations for change?

Question131: According to TOGAF, which document should incorporate the actions arising from the Business Transformation Readiness Assessment technique?

Question132: Which one of the following best describes the next step in an Architecture Compliance Review once the scope of the review has been determined?

Question133: According to TOGAF, which of the following types of architecture has major characteristics that include open system standards and general building blocks?

Question134: According to TOGAF, which of the following best describes the purpose of an Architecture Roadmap?

Question135: Which of the following best describes the purpose of the Gap Analysis technique?

Question136: TOGAF Part VII, Architecture Capability Framework recommends use of an ADM cycle for establishing an architecture practice. In this scenario which architecture would describe the organizational structure for the architecture practice?

Question137: Scenario:
Please read this scenario prior to answering the Question.
The ABC company is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer. Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average.
The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to AirLight, a competitor, because of superior customer service. The company actually has better coverage in nearly all markets than AirLight, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low. The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan.
They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board. The planning for the program has been underway for several months. The company has selected TOGAF 9 as the basis for its Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation.
The Executive Council has stated that the program should define specific initiatives to enable each regional business unit to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.
Refer to the Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.
The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At the present time, the project team is conducting an architecture development project that is focused on the customer self-service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is the best answer?

Question138: Which of the following best describes the purpose of an architecture compliance review?

Question139: Scenario:
Please read this scenario prior to answering the Question
You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems.
Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

Question140: Complete the sentence. The ADM can be viewed as the process of populating the enterprise's own
_______________with relevant re-usable building blocks taken from the more generic side of the Enterprise Continuum.

Question141: According to TOGAF, which of the following terms describes people who have key roles in, or concerns about, a system?

Question142: Which of the following best describes the concept of Boundaryless Information Flow?

Question143: What technique does TOGAF recommend that focuses on achieving business outcomes rather than just technical deliverables?

Question144: In which Phase of the ADM does the business scenario technique figure most prominently?

Question145: According to TOGAF, which one of the following best describes an enterprise architecture?

Question146: According to TOGAF, which of the following is the reason why Business Architecture is recommended to be first architecture developed?

Question147: Which of the following statements does NOT correctly describe Architecture Principles?

Question148: Complete the sentence by selecting the applicable pair of words. A/an _____is used in Phase A to help identify and understand business _____that the architecture has to address.

Question149: Scenario
Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Chief Enterprise Architect of a multinational pharmaceutical corporation. The corporation includes 30 subsidiary companies with operations in over 60 countries and products sold in over 125 countries. It has major research and development sites in over 45 locations worldwide.
The management team is deeply committed to ensuring that the corporation is a world leader in socially responsible pharmaceutical development with a business strategy that focuses on profitability through environmentally friendly operating processes as well as a commitment to disease eradication.
The operations of the corporation are subject to legal and regulatory requirements for each country where they operate. The production of prescription pharmaceutical products has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was conducting a clinical trial for a new regulated drug.
The Governing Board is concerned about the risks posed in this complex global environment. As a result the Chief Executive Officer (CEO) has appointed a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues for the corporation. The CCO reports directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture program. He has requested to be informed about the status of projects that could impact regulatory compliance. He also wants the corporate legal staff and auditors to analyze all proposed architectures to ensure that they are within the legal guidelines for each country. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance Officer, legal staff, auditors and the research organization.
Based on TOGAF, which of the following is the best answer?

Question150: TOGAF provides guidelines on how to use the ADM to establish an architecture capability. Which one of the following is NOT a correct guideline?

Question151: Which of the following describes how the Enterprise Continuum is used when developing an enterprise architecture?

Question152: Which one of the following is the most generic artifact in the Architecture Continuum?

Question153: Which of the following is described by the TOGAF Architecture Content Framework as a type of artifact that shows lists of things?

Question154: Which of the following best describes the Standards Information Base?

Question155: Complete the sentence. The TOGAF risk categorization after the implementation of mitigating actions is known as the level of risk.

Question156: Which of the following best describes the purpose of the Statement of Architecture Work?

Question157: Which of the following best describes TOGAF?

Question158: Which one of the following is considered a relevant architecture resource in Phase D?

Question159: According to TOGAF, which of the following activities is described as part of the approach in the Preliminary Phase of the ADM?

Question160: Complete the sentence. TOGAF defines five criteria for a good set of principles: Understandable, Robust, Complete, Consistent and_____.

Question161: Which of the following statements best describes the Requirements Management process?

Question162: According to TOGAF, which of the following best describes an Architecture Pattern?

Question163: Which of the following does TOGAF describe as "the structure of components, their inter-relationships, and the principles guiding their design and evolution over time"?

Question164: Which of the TOGAF architecture development phases is the first phase of an architecture development cycle, defines the scope for an engagement and identifies the stakeholders?

Question165: Complete the sentence. In TOGAF, architecture viewpoints represent ______

Question166: Scenario
Please read this scenario prior to answering the Question
Your role is consultant to the Lead Architect within a multinational semiconductor and software design company. Its largest business is in processors, although it also designs system-on-a-chip infrastructure and manufactures memory chips. A characteristic feature of its processors is their low electric power consumption, which makes them particularly suitable for use in portable devices. As well as licensing its technology, the company has several manufacturing divisions.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
The company has defined a strategic architecture to improve its ability to meet customer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A Based on all of these factors they have produced a risk assessment. They have also completed the Implementation and Migration Plan v0.1, the draft Architecture Roadmap, and the Capability Assessment deliverables.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
Refer to the Scenario
You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF, which of the following is the best answer?

Question167: Complete the sentence. The Architecture Board is typically responsible and accountable for achieving all of the following goals except ___________

Question168: Which one of the following lists the five quality criteria for defining Architecture Principles?

Question169: Which one of the following statements about TOGAF Building Blocks is NOT true?

Question170: Which model within TOGAF is closely related to the concept of Boundaryless Information Flow?

Question171: Complete the sentence: TOGAF provides a set of reference materials for establishing an architecture function within an organization known as the_________.

Question172: Which one of the following best describes the Architecture Vision document?

Question173: Scenario
Please read this scenario prior to answering the Question
You have been assigned the role of Chief Enterprise Architect within a leading outsourcing services company. The company has over 20,000 outsourcing professionals and works on some of the world's largest outsourcing projects. Outsourcing services include business processes, infrastructure, and service management. The company also provides business consulting services.
With numerous service areas and a large number of diverse engagements in progress at any given time, overall engagement management within the company has become challenging. The company does not want to risk Its outstanding reputation or its international certifications and CMM ratings.
The company has an established an Enterprise Architecture program based on TOGAF 9, sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture Board has been formed comprised of IT staff executives and executives from the major service areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to create a strategic enterprise architecture to address these issues. The EA team has defined a framework and held workshops with key stakeholders to define a set of architecture principles to govern the architecture work.
They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period.
This includes a solution architecture including three distinct transformations.
The CIO has made it clear that prior to the approval of the detailed Implementation and Migration plan, the EA team will need to assess the risks associated with the proposed architecture. He has received concerns from some of the vice presidents across the company that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?

Question174: Which phase of the ADM focuses on the governance and management of the Architecture Con-tracts that cover the overall implementation and deployment process?

Question175: Scenario
Please read this scenario prior to answering the question
Your role is that of the Lead Architect working for a government agency responsible for immigration, customs, and border control. The agency was formed by consolidating several smaller government agencies. The agency has established an Enterprise Architecture practice based on TOGAF 9. The CIO is the executive sponsor and has appointed an EA steering team to oversee the practice.
There has been a considerable increase in security requirements and immigration service requests in recent years, which have expanded the scope and size of the operations of the agency. As a result, the existing Information Technology architecture no longer meets the required service levels. A significant Enterprise Architecture (EA) initiative is in progress with the opal to improve customer responsiveness and satisfaction, and improve the overall operational efficiency of the agency.
The current EA staff members were internal appointments based on a request from the EA steering team to supply a number of suitable individuals for the EA effort. Collectively, they possess a broad range of IT and business analysis skills. However, the CIO has expressed concern about the diverse range of experience within the team. There is concern that the EA staff may be lacking in some of the critical skills that are required to properly conduct EA activities. It had been assumed that any EA-related skill gaps would be overcome by on-the-job mentoring from the senior members of the EA staff. Each architect was expected to attend a TOGAF training course and participate in other skill development activities.
A recent review of the EA program revealed that many EA staff members, despite attending multi-day training courses, were not proficient in analyzing or creating the models and artifacts required for their assigned architecture projects. Stakeholders have observed errors and inconsistencies in artifacts and deliverables being submitted for review.
Refer to the Scenario
The CIO has asked you to recommend a professional development plan for the EA staff in order to address the findings raised in the recent review.
Based on TOGAF, which of the following is the best answer?

Question176: In which ADM phase are the business principles, business goals and strategic drivers first validated?

Question177: What class of architectural information within the Architecture Repository defines processes that support governance of the Architecture Repository?

Question178: Which of the following best describes a purpose of the Gap Analysis technique?

Question179: Which of the following is a re-usable artifact that is used to create architecture models addressing stakeholder concerns?

Question180: Complete the sentence. According to TOGAF, all of the following are responsibilities of an Architecture Board, except ______________________.